MIL-I-85889(AS)
4.3.4.8 Test readiness review. When specified in the contractor order, and prior to the initiation of the design
verification testing, the contractor shall hold a test readiness review with the participation of the contracting activity.
The contractor shall present data to demonstrate the following:
a.
The test objectives are achievable
b.
The test article's quality and "as-built" configuration are documented and traceable to serialized components
c.
The test methodology is consistent with the test objectives
d.
The test objectives and methodology are understood by the supporting activities.
4.3.4.9 Nomenclature request. When specified in the contract or order, the contractor shall prepare a
Nomenclature Assignment Request (NAVSEA 503011) for an EX number in accordance with MIL-STD-1661. The
request shall be made available via the contracting activity no later than 60 days prior to the Critical Design Review
4.3.4.10 Hazard assessment test plan. Based on hazard analysis (see 4.2.2.7) and anticipated reactivity of
the igniter, the contractor shall develop a test plan for hazard classification (see 3.5.2.1) and sensitivity assessment
(see 3.5.2.2). As a minimum, the requirements of MIL-STD-1648 and DOD-STD-2105 shall be addressed. When
specified in the contract or order, the test plan shall be made available to the contracting activity no later than
30 days prior to the Critical Design Review.
4.3.4.11 Review agenda. When specified in the contract or order, the contractor shall provide the agenda for
the Critical Design Review The agenda shall set forth the place, time, date, purpose, and objectives of the review.
The agenda shall be made available to the contracting activity no later than 30 days prior to the Critical Design Review.
4.3.4.12 Critical Design Review. When specified in the contract or order and at the conclusion of the Phase
II effort, the contractor shall conduct a Critical Design Review in accordance with MIL-STD-1521. Upon satisfactory
completion of the Critical Design Review the contracting activity will authorize initiation of Phase Ill.
4.3.4.13 Review minutes. When specified in the contractor order, the contractor shall prepare a record of the
results of the Critical Design Review. A draft copy of the review minutes shall be made available to the contracting
activity for review and comment no later than 30 days follwing the review. The final review minutes shall be distributed
no later than 15 days after receipt of the contracting activity's comments.
4.3.5 Configuration control. At the inception of Phase II, the contractor shall institute control of the configuration
identification (as defined in DOD-STD-480) for the igniter design. The methods of configuration control may be
selected by the contractor as long as they provide for the systematic evaluation, coordination. and implementation
of changes.
4.3.6 Reliability assessment.
4.3.6.1 Reliability program. When specified in the contractor order, the contractor shall establish, implement,
and document a reliability program using MIL-STD-785 as a guide Each igniter tested in Phase II shall be evaluated
for reliability. If any igniter fails during one of these tests, the contractor shall diagnose the failure to root causes
and provide corrective actions acceptable to the contracting activity.
4.3.6.2 Reliability growth curve. A reliability growth curve shall be maintained throughout Phase II to assess
the igniter demonstrated (pass/fail) reliability at 90 percent confidence.
4.4 Phase Ill--Design Qualification.
4.4.1 Fabrication
4.4.1.1 Manufacture of environmental test items. The contractor shall manufacture environmental test items
in accordance with the approved Level 3 drawings.
17