MIL-I-12822C(MU)
these designs accordingly. The contractor may, however, In
connection with non-mandatory designs, and with the approval
of the Government, design alternate inspection equipment or
use comparable commercial equipment to facilitate his opera-
tions. Such contractor prepared designs or commercial equip-
ment selections must be approved by the Government prior to
fabrication or procuring of the equipment. Designs shall be
submitted for approval as specified in 6.3.5.
6.3.4 Contractor designs. - Contractor designs are designs
of inspection equipment for which the Government has assigned
design responsibility to the contractor. Contractor designs
shall be supported by detailed drawings which depict all infor-
mation necessary to completely fabricate, calibrate and operate
an item of inspection equipment. This requires that the neces-
sary views, dimensions, materials, finish, notes, operating
and calibration instructions be properly depicted In accordance
with approved practices to the extent that further calculation
or clarification will not be required. Unless otherwise speci-
fied, contractor designs may be developed on the format the
contractor normally employs in his equipment design procedure
provided such format reflects the detail and information speci-
fied above, subject to the following controls: All submitted
contractor designs shall conform to MIL-D-1000, Category E,
Form 2. Legibility and reproducibility shall permit conven-
tional making of clearly understandable, high contrast repro-
ductions. Contractors shall submit one copy of final designs
as a rolled set. Designs shall be submitted for approval as
specified in 6.3.5.
6.3.5 Submission of contractor designs. - Unless other-
wise specified on the EL, all designs of equipment for inspec-
tion of defects classified as critical and major shall be sub-
mitted for approval to the Commanding Officer, Picatinny Arsenal,
ATTN: SMUPA-ND1. All other desibns of inspeciton equipment shall
be approved by the inspection element of the agency administering
the contract; submission shall be as directed by the contracting
officer. Partial submission of Inspection equipment designs is
permissible and encouraged. However, the Arsenal cpompletion date
for design review will be based on the date of the final sub-
mission of designs. Picatinny Arsenal design review will be
accomplished normally within one month after receipt.
Custodian:
Preparing Activity:
Army-MU
Army-MU
Project No. 1340
13